What the Missing Link is and why it has that name
The Missing Link is a 13.3 km stretch of the Mumbai–Pune Expressway between the Khopoli exit in Raigad district and Kusgaon near Lonavala in Pune district. It was built by the Maharashtra State Road Development Corporation (MSRDC), the state body that owns the Expressway. For the vehicles allowed on it, it replaces the climb through the Khandala ghat, also called the Bhor Ghat, which reports put at 19 to 19.8 km.
The name comes from a gap in the original road. When the Expressway opened in 2002, it had no road of its own through part of the ghat. Between the Adoshi tunnel and the Khandala exit, Expressway and old highway traffic share one corridor, as Construction World describes it. Autocar India reports that the bypass was part of the original plan but was shelved over cost, engineering and environmental problems until its approval in 2018. Work began in 2019.
PTI reported at the opening that the new road is expected to make the Expressway fully access-controlled. Officials put the saving at about 6 km and 20 to 30 minutes. At the inauguration, Chief Minister Devendra Fadnavis said it should be called the Connecting Link, since nothing is missing any more. The Highway Police notification of 26 October 2026 uses both names, so you may see either.
Opening dates: inaugurated on 1 May 2026, open both ways by 3 May
Chief Minister Devendra Fadnavis inaugurated the Missing Link on 1 May 2026, Maharashtra Day, at the Khalapur end in Raigad district at about 1 pm, PTI reported. He then drove on the Lonavala-bound carriageway with Deputy Chief Minister Eknath Shinde beside him. The new road stayed closed until the ceremony, on the first day of a long weekend, so the old ghat jammed for hours and the Chief Minister apologised to stranded commuters.
The two directions did not open together. The Pune-bound side opened after the ceremony. On the morning of 2 May, the Free Press Journal reported the Pune to Mumbai side still shut for finishing work and safety checks. Officials then expected it to open within two to three days. Autocar India had said on 1 May that motorists could use the route from 2 May.
By 3 May the Free Press Journal was describing the link as open to traffic, with MSRDC warning drivers not to stop for photographs. We could not confirm the hour the Mumbai-bound side opened. So if you see both dates given, both are partly right: 1 May is the inauguration and the first day of Pune-bound traffic, and 2 May is the date given for general use.
Key numbers: tunnels, bridge, lanes and cost
The Missing Link is made up of two tunnels and two viaducts, one of which is a cable-stayed bridge over Tiger Valley, as Autocar India and Construction World describe it. It carries eight lanes, four in each direction. Published figures for the tunnels and the cost differ between reports, so the table gives ranges and says who reported each figure.
The longer tunnel passes about 180 m below Lonavala Lake, according to Autocar India and Construction World. Cross passages every 300 m link the Pune-bound and Mumbai-bound tunnels, so traffic can be moved across in an emergency. Construction World names the contractors: Navayuga Engineering for the tunnels and Afcons Infrastructure for the viaducts, including the cable-stayed bridge. Navayuga’s own site credits it with the tunnel, and The Bridge Chronicle credits Afcons with the bridge.
The cost is given three ways. Autocar India and Moneylife report ₹6,695 crore, the Chief Minister rounded it to ₹7,000 crore at the opening, and Construction World gives a revised ₹7,181 crore. We could not confirm which is final, because MSRDC’s website did not load when we checked. The MSRDC release quoted by PTI also counts 5.86 km of existing road between Khalapur and the Khopoli interchange, widened from six to eight lanes, as part of the project.
| Item | Reported figure | Who reported it |
|---|---|---|
| Length | 13.3 km, Khopoli exit to Kusgaon | PTI, Autocar India, Moneylife |
| Ghat route it bypasses | 19 to 19.8 km | Moneylife (19 km), Autocar India (19.8 km) |
| Distance saved | About 6 km | PTI, citing officials; Autocar India |
| Time saved | 20 to 30 minutes | PTI, citing officials; Autocar India gives about 25 minutes |
| Lanes | Eight, four in each direction | Autocar India, Construction World |
| Longer tunnel | About 8.9 km (8.92 km in most reports) | Autocar India, Construction World |
| Shorter tunnel | 1.6 to 1.75 km | Autocar India (1.6 km), Construction World (1.75 km) |
| Tunnel width | About 22.3 m, listed by Guinness World Records as the widest underground road tunnel | Autocar India, Construction World |
| Tiger Valley bridge | 650 m long, with 182 m pylons and 240 stay cables | PTI, citing officials; Construction World |
| Bridge deck height | About 125 m above the valley | Autocar India only; we could not confirm it elsewhere |
| Cost | ₹6,695 crore to ₹7,181 crore | Autocar India and Moneylife (₹6,695 crore); Construction World (₹7,181 crore, revised) |
Other reports give a shorter tunnel of up to 1.9 km and tunnel widths of up to 23.75 m. Treat every row as a reported figure, not as MSRDC’s final number.
Who may use it: cars and passenger buses, not goods vehicles
Private cars, jeeps and other non-transport light motor vehicles may use the Missing Link, and so may passenger buses and other passenger vehicles. That is the wording of a notification signed on 26 October 2026 by Maharashtra’s Additional Director General of Police (Traffic), as reported by Punekar News and Swarajya. It applies from 1 November 2026 until further orders. The reports we read do not mention taxis by name.
All goods vehicles are barred, including small ones such as pickup vans and the Tata Ace, and so are vehicles carrying flammable, explosive or other hazardous material. Goods vehicles had already been kept off in the first phase, from 1 May to 31 October 2026, pending a review. The October notification made the ban permanent, citing tunnel safety, and banned vehicles must keep to the old alignment through the ghat. The Highway Police ask you to check that your vehicle category is allowed before you enter.
Two-wheelers and three-wheelers cannot use the Missing Link because they are not allowed on the Expressway at all. The speed limit is 100 km/h for cars and other light motor vehicles and 80 km/h for passenger buses. Punekar News reports that the notification does not book a speed within 5% of the limit. On the old ghat route the limits stay at 60 km/h for cars and 40 km/h for buses, as our Expressway guide explains.
Missing Link toll charges: no separate toll
There is no separate toll for the Missing Link. A car still pays ₹320 for one full Expressway journey, the rate in force since 1 April 2023, and FASTag still deducts it at Talegaon (Urse) and Khalapur. Deputy Chief Minister Eknath Shinde said no separate toll would be levied (Moneylife, 29 April 2026), and PTI reported on 1 May 2026 that no toll rise had been proposed, including at Khalapur.
So the Pune to Mumbai toll for a car via the Missing Link is ₹320 one way: ₹240 at Talegaon (Urse), the first plaza from Pune, and ₹80 at Khalapur. From Mumbai it is ₹240 at Khalapur and ₹80 at Talegaon. A return trip is ₹640, and a car without a valid FASTag pays double. Our Mumbai–Pune Expressway toll charges guide has the rates for other vehicles and the old highway.
Both plazas lie outside the bypassed stretch. Khalapur is below the ghat on the Mumbai side and Talegaon is on the Pune side. So the route you take through the ghat does not change the toll, as Autocar India also reported. Leaving the Expressway at Lonavala can change it: drivers have reported a Lonavala exit and re-entry billed as two journeys, and the Missing Link does not serve Lonavala.
Missing Link directions from the Pune side and the Mumbai side
From Pune, you join the Expressway at Kiwale and pass the Talegaon (Urse) toll plaza first. The Missing Link starts at Kusgaon, near the Sinhgad Institute outside Lonavala, where the new road leaves the old alignment. It rejoins at the Khopoli exit at the foot of the ghat, about 6 km before the Khalapur toll plaza, and the Expressway continues from there to Kalamboli.
From Mumbai, you pass the Khalapur toll plaza and then the 5.86 km stretch widened to eight lanes for the project. The Missing Link leaves the old alignment at the Khopoli exit, runs through the tunnels and over Tiger Valley, and rejoins it at Kusgaon, before the Talegaon (Urse) plaza. We found no published description of the direction boards at either split, so we cannot quote them. Official notices use both names, Missing Link and Connecting Link.
The Missing Link does not serve Lonavala or Khandala. Autocar India reported at the opening that travellers heading to Lonavala still have to use the older ghat section, and the Khandala exit lies on that section. If you are going to either town, stay on the old alignment. Some travel blogs say Lonavala can be reached from the Kusgaon end; we could not confirm that from MSRDC or the Highway Police, so follow the boards on the day.
| Direction | Main toll plaza before it | Where it starts | Where it rejoins | Exits it does not serve |
|---|---|---|---|---|
| Pune to Mumbai | Talegaon (Urse), ₹240 for a car | Kusgaon, near the Sinhgad Institute | Khopoli exit, about 6 km before Khalapur | Lonavala and Khandala |
| Mumbai to Pune | Khalapur, ₹240 for a car | Khopoli exit, about 6 km after Khalapur | Kusgaon, near the Sinhgad Institute | Khandala and Lonavala |
End points as reported by PTI and Construction World; the Sinhgad Institute landmark is from Construction World. The Lonavala entries follow Autocar India, and we found no official ramp map. The overhead boards on the day take precedence.
Closures, safety and what to do if the Missing Link is shut
The longest closure we found followed a landslide. At about 4 am on 6 July 2026, heavy rain brought rocks and soil down near the exit of Tunnel 2, the longer of the two. MSRDC stopped Mumbai-bound traffic as a precaution, PTI reported. The Bridge Chronicle reported on 7 July that two lanes reopened at about 10:10 pm, more than 18 hours later, after slope inspections. Mumbai-bound traffic went over the old ghat in the meantime, and that route had landslides of its own.
Shorter disruptions have followed. Traffic in the Mumbai-bound tunnel was restricted from 12 noon to 3 pm on 12 August 2026 for maintenance and a mock drill (Free Press Journal). One lane was stopped for a time after two accidents before dawn on 6 October 2026 (The Bridge Chronicle). Stopping is not allowed anywhere on the Expressway. The Free Press Journal reported in May that the tunnels and bridges are watched by CCTV around the clock, and that vehicles which stop are reported to the Highway Police.
If the Missing Link is shut, traffic is sent over the old ghat route through Lonavala and Khandala, which is slower. Check live traffic and any MSRDC or Highway Police advisory before you leave, especially after heavy rain, and keep extra time for a flight. When you ask Yellow Plate Wala for a Pune to Mumbai quote, mention any halt in Lonavala or Khandala, because those towns are reached by the old ghat route, not the Missing Link.
Common questions
What is the Missing Link toll charge for a car?
There is no separate toll for the Missing Link. A car pays ₹320 for one full Expressway journey either way, unchanged since 1 April 2023, and FASTag deducts it at Talegaon (Urse) and Khalapur. The Deputy Chief Minister said before the 1 May 2026 opening that no extra toll would be charged.
What is the Pune to Mumbai toll for a car via the Missing Link?
It is ₹320 one way, the same as by the old ghat route. FASTag deducts ₹240 at Talegaon (Urse) and ₹80 at Khalapur. A return trip costs ₹640, and a car without a valid FASTag pays double.
Where does the Missing Link start and end?
It runs 13.3 km between Kusgaon near Lonavala on the Pune side and the Khopoli exit on the Mumbai side. Coming from Pune, it starts at Kusgaon after the Talegaon (Urse) plaza. Coming from Mumbai, it starts at the Khopoli exit, about 6 km after the Khalapur plaza.
Where is the Lonavala end of the Missing Link?
It is at Kusgaon, near the Sinhgad Institute, on the Expressway itself. You cannot be picked up or dropped there: stopping is prohibited and auto-rickshaws are not allowed on the Expressway. We found no official reference to an auto stand. For Lonavala town, take the Lonavala exit on the old alignment.
Which vehicles are allowed on the Missing Link?
Private cars, jeeps and other non-transport light motor vehicles, and passenger buses and other passenger vehicles. Goods vehicles of every size, pickups included, and vehicles with hazardous cargo are banned under a notification of 26 October 2026, permanent from 1 November 2026. Two-wheelers are not allowed on the Expressway at all.
How long is the Missing Link and how much time does it save?
It is 13.3 km long and replaces a ghat route of 19 to 19.8 km, saving about 6 km. Officials put the time saved at 20 to 30 minutes. It has two tunnels, the longer about 8.9 km, and a 650 m cable-stayed bridge over Tiger Valley.
Sources and official information
Figures and rules on this page were checked against the sources below on 18 November 2026. They change; confirm with the official source before you travel.
- ThePrint (PTI), 1 May 2026: Missing Link opens; cost, bridge figures, 19.16 km corridor and no toll rise
- Autocar India, 1 May 2026: Maharashtra CM inaugurates the Mumbai–Pune Expressway Missing Link
- Moneylife, 29 April 2026: Missing Link opens on 1 May with no extra toll
- Free Press Journal, 2 May 2026: Pune to Mumbai side of the Missing Link still shut after the inauguration
- Construction World, 3 May 2026: tunnel and bridge contractors, lanes and project figures
- The Bridge Chronicle, 7 July 2026: Missing Link reopens after an 18-hour closure caused by a landslide
- Punekar News, 26 October 2026: Missing Link ban for goods vehicles, speed capped at 100 km/h for cars